The City of Jackson Board of Aldermen approved a $347,461 expenditure to replace screw pumps at the city’s wastewater treatment plant during its regular meeting on Monday, Oct. 19.
The replacement was approved after one of the plant’s four screw pumps broke and is no longer operational. The likely cause of the emergency failure was not maintenance issues, but the extended mechanical load since it was installed in 1988.
The additional cost was approved as a change order with Penzel Construction as part of the city’s improvement project at the wastewater treatment plant. The approval is the largest change order with the project to date, with the city previously approving $270,399 in changes over five different change orders.
Senior Project Engineer Daniel Ritchason with Horner & Shifrin, which is providing professional engineering services for the wastewater treatment project, recommended the complete replacement of all four screw pumps and shaft adapters.
Ritchason said the screw pumps, which hydraulically lift wastewater at the front of the plant to allow gravity flow throughout the treatment facility, are central to the operation of the plant. He said the plant can still be operational with one out of use, but if another screw pump breaks, the city would not be able to handle peak conditions.
“These screw pumps are 38 years old, and they’re really only built for a 30-to-35-year useful life,” Ritchason said. “All four of these screw pumps have been experiencing the same load, same weather, same conditions for the last 38 years, so when one breaks that makes us scared about the next three.”
The wastewater treatment improvement plan originally included the refurbishment of the current screw pumps, including adding two inches of steel to restore the shafts and flights back to their original condition and dimensions.
Ritchason said the repair work was originally going to be done by Fab Tech Wastewater Solutions from the St. Louis area, but the company is no longer able to fulfill their contract obligations. Fab Tech filed for bankruptcy in April this year.
Ritchason said is has been difficult to find a reputable company that specializes in screw pump rehabilitation like Fab Tech. In addition, after visual inspection once the broken screw pump was removed, more rehab work was needed than initially intended.
The rehab option was estimated to cost $131,105, but Ritchason said they were not confident in a replacement company and if vibration testing failed, they would have to add an additional $205,000 in balancing work.
“If it’s not done correctly and the screws are off balance, that will then further damage all of the equipment, the bearings, motors, everything,” Ritchason said. “It’ll be essentially catastrophic to the project and the plant.”
In addition, if the city decided to continue with rehabilitation work instead of replacing the screw pumps, it would add an additional 32 weeks to the project. “We have to send each screw one at a time, and that’d be about an eight to 10 week total over the course of installation per screw,” Ritchason said.
Aldermen questioned why the replacement was not a part of the original plan, since the screw pumps were beyond their 35-year lifespan. Ritchason, who wasn’t part of the original planning process, said the decision was likely made after its inspection in 2016 found the pumps to be in good maintenance shape. He said the rehabilitation work would likely extend the screw pumps’ lifespan by a minimum 10 to 15 years.
Alderwomen Katy Liley said the additional expense was discouraging, as the cost to replace the screws could have been included in the part of the bond funding if it was originally part of the project.
“Representing Horner & Shifrin, our recommendation is to replace the screws,” Ritchason said. “I know it’s really costly, but it saves time, and it’ll save money over the course of the next 30 to 35 years. It’ll be installed, and then we won’t have to think about it.”
Ritchason said the new screws would be delivered from a supplier in Texas within eight to 10 weeks. The screws will then be installed on-site by Penzel Construction.
In other action:
• The aldermen approved a text amendment to the city’s code of ordinances allowing developers to obtain building permits in new subdivisions before all public infrastructure is fully completed.
The amendment, which was requested by the city’s economic development board, allows limited early construction after the final plat is recorded and a performance guarantee is approved.
Builders would be allowed up to three building permits or 20% of the total lots within the subdivision, whichever is greater, while street and utility contractors continue completing the required subdivision improvements, including streets, utilities, stormwater and street lighting.
The early building permits would be limited to lots contiguous to one another in order to prevent scattered development and ensure that early construction does not occur in unfinished portions of the subdivision.
A public hearing was held before the vote with no public input.
• The board approved a change order with CE Contracting, Inc., reducing the total contract price by $69,880 for the sewer extension from Williams Creek to South Old Orchard Road completed in July.
Public Works Director Janet Sanders said the reduction was primarily due to less rock work than expected during construction.
The final cost for the project is $327,039. The project was co-funded by KB123, LLC, and The Villas of West Park, LLC, with both entities contributing $85,000 toward the construction cost.
• The board approved renewal contracts with Auxiant, Roundstone Management Ltd. and The Standard for the city’s medical, dental, vision and life insurances. Auxiant will remain the city’s third-party administrator for health care insurance.
Overall, the renewals for the medical resulted in around a 10% increase to the employees’ and city’s cost. Dental and vision are all employee paid benefits. Dental rates will remain the same. Vision will have an 8%, or $0.80 per month, increase on the employee-only rate.
The city plans to switch to TrueRx as its pharmacy benefit manager to help save costs on the pharmacy side. The contract with TrueRx was not yet ready for approval and is expected to be voted on at the aldermen’s next meeting.
• The board approved a $9,170 change order with Herzog Excavating & Demolition, LLC, to remove and dispose of additional stockpiled brush at the city’s yard waste disposal site.
• The board approved a corrected final change order with Fronabarger Concreters for the Deerwood roundabout project. A mistake was found in a unit price, resulting in a $720 reduction in the previously approved total contract price. The total construction cost for the project changed from $1,070,555 to $1,069.835.
• The board approved a renewal of its e-waste disposal services agreement with Midwest Recycling Center. The contract will now be in effect through Oct. 22, 2027, under the same terms and conditions as the original agreement.
• The board approved a new master services agreement with Klingner & Associates, P.C. The city’s previous agreement was with Koehler Engineering & Land Surveying, Inc., which was acquired by Klingner & Associates, P.C.
To ensure that Klingner & Associates is formally bound by the same terms and conditions applicable under the city’s previous agreement, a new master services agreement was prepared with Klingner & Associates, P.C.
• Uptown Jackson Revitalization Organization Executive Director Kaci Hubbard presented the organization’s annual report to the board during study session.
Hubbard estimated that more than 900 volunteer hours have been served by area residents this year to help make UJRO’s work possible.
• Members of Boy Scout Troop 4011 attended the meeting, working on one of their Eagle merit badges. Scouts asked questions of the board and city officials to learn more about how local government works.