The Missouri Department of Transportation held a public meeting at the Cape Girardeau Career & Technology Center Aug. 27 to discuss the I-55 Exit 93 interchange in Cape Girardeau.
The Exit 93 interchange connects southbound Kings-highway traffic to Interstate 55 and Route 74. The bridge in this location is long and curved, and it is referred to as a “flyover.” It was constructed in 1961 and currently carries more than 6,000 vehicles a day. It is in poor condition and needs to be replaced.
“After MoDOT and consulting engineers reinspected the flyover bridge, it was determined the bridge could be rehabilitated to extend its life,” explained MoDOT Project Manager Tim Pickett.
The flyover will receive a new deck in 2026. This should add an additional 20 years to the bridge’s lifespan. Eventually, it will be replaced with a new bridge that will cross I-55 to the north of its current location.
“Additionally, the project will implement phase one of the preferred plan for Exit 93 that was shared at the public meeting on July 27, 2022,” said Pickett.
Phase 1 includes replacing the signals at Silver Springs Road with a two-lane roundabout to improve safety at that intersection.
The project will also close access ramps at Route 74 and rehabilitate the northbound I-55 bridges over Missouri route 75 and the BNSF railroad tracks.
While work is being done on the northbound I-55 bridges, traffic will be diverted from the northbound I-55 lanes to one of the southbound lanes, where there will then be head-to-head traffic.
Tentatively, the project is expected to be let in February 2026. Construction could begin as early as April 2026.
In anticipation of the flyover closure, signals will be installed at the Route 74/I-55 interchange. Motorists will be encouraged to use this access to I-55 during construction.
The construction of the roundabout at Silver Springs Road and Business 61 will be staged to allow movement through the intersection.
Completion is anticipated in fall/winter 2028.Completion of the roundabout will represent one phase of the improvement plan for the interchange. Additional phases could be completed as funding becomes available in the future.
When the project is ultimately completed with Phase 3, there will be a new bridge over I-55 with roundabouts on both sides.
Missouri Route 74 will be rerouted through farm fields using a new roadway that will join the new bridge on the west side of I-55. The old Route 74 that now passes under I-55 will no longer pass under the Interstate. It will end in cul-de-sacs on both sides of I-55.